Asphalt Roofing Shingles Information Sheet
View information on asphalt roofing shingles.
Fences
- Do I need a permit for a fence?
No (maximum height of 6 feet in residential areas). - Are there any other height restrictions?
Yes. Commercial zones may have a fence with a height up to 8 feet. Also, corner and front yard heights can be no higher than two and one-half feet above the ground.
Where can my fence be located?
Fences may be located on the property line (if property line is questionable, consult with a neighbor or have the area surveyed). - What are the requirements to the city?
The city needs a site plan of the area to be fenced. - Are there any other limitations?
Yes. Barbed wire cannot be used and the fence must have a salvage finish on the top and bottom. - Who can I contact for more information?
If you have further questions, please contact the Building & Zoning Official.
Minnesota State Contract License Law
View information on statewide Contractor and Remodeler License Law.
Single-Family Stairway Guards Information Sheet
Access information on specifications for single-family stairway guards.
Inspection Information
These requirements must be met before obtaining an inspection from the building official.
- Footing Inspections
- Engineer’s soil report available, if applicable
- Erosion control in place when required
- Excavation / form work completed; if reinforced, secured per code
- Inspection record card available
- Job site address posted during the entire construction process
- Submit footing elevation verification by the surveyor to the city engineer division prior to foundation wall construction
- Framing Inspections
- All framing, fire blocking, and bracing in place and completed
- Approved site plans available
- Building and fireplace inspection record cards posted
- Enclosure / container provided on site for all construction-related rubbish; contents periodically disposed to prevent littering of property or adjacent areas until final inspection approval
- Engineer approved and signed shop drawings for all trusses, girders, and hangers must be posted
- Rough-in electrical, plumbing, and heating work inspected and approved
- Insulation Inspections
- Framing work inspected and approved
- Insulation and vapor barriers in place and completed
- Insulation protected from the weather
- Final Inspections
- Address numerals installed on building and height
- All referenced inspections on this card are inspected and approved
- As-built survey submitted to the city engineering division
- Final electrical, plumbing, and heating work inspected and approved
- Finish grading and building completed and ready for occupancy
- Inspections record card posted